Our involvement at the Royal Connaught Park, Bushey has been over a period of 15 years and 3 separate phases of works.
Phase I which commenced in 2006 comprised the refurbishment of the Grade II listed former Royal Masonic School as residential apartments and including a basement leisure centre/swimming pool constructed below the school hall (used as a Harry Potter Set).
Revisions to the existing buildings included the provision of new stair/lift access and formation/installation of mezzanine floors within existing 60deg. roof spaces.
Phase II which commenced in 2012 involved the completion of the refurbishment of the main quad and ancillary buildings.
This phase also included a 150 space underground carpark which was constructed as a ‘cut and fill’ operation and at completion was restored in keeping with the surrounding grass areas.
Phase III which was commenced in 2016, comprised a second quad constructed as a podium deck over a 200 space underground car park and providing a further 160 new build apartments.
Phase III was completed in spring 2018 and is now fully let/sold.